This is a 17 minute long narrated collection of stop-action, video, and photos of the first two trips out to the east coast to build our (not from a kit) a-frame (~$40k CDN). For cost breakdown and other details see: nakamoto.ca/page/projects/aframe
The first trip was 11 days in April and the second was 5 days in May. The narration describes the project and some of the construction details.
For more cost and more details, links to my planning documents, the book I used, etc. please visit the project page on my personal website: nakamoto.ca/page/projects/aframe
0:00 Introduction
0:01 CAPE BRETON AFRAME BUILD PRELIMINARY SITE VISIT APRIL 1, 2023
0:41 FOUNDATION GRAVEL TO POST, BEAMS
1:33 FOUNDATION STRAIGHTENING, LEVELING, SQUARING, BRACING
2:51 TRUSSES CUTTING ANGLES AND ASSEMBLING JOISTS
4:11 TRIANGLES ASSEMBLING AND RAISING TRIANGLES AND ROOF
4:52 TRIANGLES MORE TRIANGLES AND ROOF SHEATHING
5:56 ROOF SHEATHING, LOFT FLOOR
8:37 ROOF SHEATHING, MEMBRANE, STEEL ROOF
9:32 REST DAY + MAIN FLOOR WORK UNDERSHEATHING, SET UP VENTS, INSULATE
11:17 BACK WALL FRAMED, SHEATHED, TYKEK, WINDOWS, DOOR
11:26 FLOOR AND FRONT WALL FINISHED MAIN FLOOR, STARTED FRAMING FRONT WALL
12:04 LAST DAY FRONT WALL, DECK, FINISHED ROOF